Planning a well
Every well starts with a target: a reservoir identified by geologists and geophysicists from seismic data and nearby wells. Engineers then design the well's trajectory, its casing strings and its drilling fluid programme. The central constraint is the window between pore pressure (the pressure of fluids in the rock) and fracture pressure (the pressure at which the rock breaks). The drilling fluid must stay heavy enough to hold back formation fluids and light enough not to fracture the formation.
Onshore, a lease or pad is built with access roads, and one pad increasingly hosts many wells. Offshore, a site survey checks the seabed and shallow hazards before a rig arrives. Permits, landowner agreements and environmental approvals all come first.
Drilling rigs
| Rig type | Where it works | Notes |
|---|---|---|
| Land rig | Onshore | Many can "walk" between wells on a multi-well pad without being dismantled |
| Jack-up | Shallow water, typically up to about 150 m | Legs are lowered to the seabed and the hull is jacked above the waves |
| Semi-submersible | Deep water | A floating rig held in place by moorings or dynamic positioning |
| Drillship | Deep and ultra-deep water | A ship-shaped, self-propelled rig using dynamic positioning |
| Platform rig | Offshore production platforms | Drills development wells from a fixed installation |
The drilling process
Drilling begins with the spud. A top drive rotates the drill string, a column of steel drill pipe with the drill bit at its end. Most wells today use PDC bits (polycrystalline diamond compact cutters fixed to the bit body), while roller-cone bits are still used in some formations.
Drilling fluid, or mud, is pumped down the inside of the drill pipe, out through nozzles in the bit and back up the annulus between the pipe and the hole. It does several jobs at once:
- Cools and cleans the bit.
- Carries rock cuttings to surface, where shale shakers screen them out.
- Balances formation pressure with its hydrostatic weight.
- Stabilises the borehole wall until casing is run.
The driller watches rate of penetration, weight on bit, rotary speed, torque, pump pressure and mud volumes continuously. Changes in these are often the first sign of a problem downhole.
Casing and cementing
A well is built like a telescope. At planned depths drilling stops, and a string of steel casing is run and cemented in place before drilling continues with a smaller bit:
- Conductor holds back loose surface soils.
- Surface casing protects freshwater aquifers and provides a base for the blowout preventer.
- Intermediate casing isolates troublesome or pressured zones.
- Production casing or liner runs to the reservoir and contains the well's production.
Cement pumped into the annulus bonds the casing to the rock and seals zones from one another. Tools such as cement bond logs check that the seal is sound, which is central to well integrity for the life of the well.
Directional and horizontal drilling
Few wells today are simply vertical. A directional well turns away from vertical at a kick-off point, builds angle through a curve and, in a horizontal well, continues sideways through the reservoir in a lateral. In shale plays, laterals are commonly two to three kilometres long, and some are far longer.
Steering is done with downhole mud motors fitted with a slight bend, or with rotary steerable systems. Measurement while drilling (MWD) tools report inclination and direction to surface, usually through pressure pulses in the mud, and logging while drilling (LWD) tools measure the rock as it is drilled so that geologists can "geosteer" the lateral to stay in the best part of the reservoir.
In the oil sands, SAGD depends on the same technology: two parallel horizontal wells drilled a few metres apart, one above the other, for steam injection and production.
Well control
If formation pressure exceeds the pressure exerted by the mud column, formation fluids can flow into the well. This is called a kick. Crews watch for early signs, such as a gain in mud pit volume or flow from the well with the pumps off.
The blowout preventer (BOP) stack on the wellhead is the main barrier. Annular preventers seal around any pipe, ram preventers close on the drill pipe, and blind shear rams can cut the pipe and seal the well completely. Once the well is shut in, heavier "kill" mud is circulated to restore control, using established methods such as the driller's method or the wait-and-weight method.
Completing the well
Reaching total depth is only half the job. Completion turns a drilled hole into a producing well:
- Perforating. Explosive charges punch holes through the casing and cement into the reservoir.
- Stimulation. In tight rock, hydraulic fracturing pumps water, sand (proppant) and additives at high pressure to open fractures that the sand then props open. Horizontal wells are fractured in many stages, often using the "plug-and-perf" method. Carbonate reservoirs may be stimulated with acid instead.
- Production equipment. Tubing, packers, the wellhead and the valve assembly known as the "Christmas tree" are installed, followed by artificial lift such as rod pumps, gas lift or electric submersible pumps as the well needs it.
Drilling performance and data
Rigs are usually hired on dayrate contracts (see oilfield services contracts), so time is money. Operators track days per well, metres or feet drilled per day, and above all non-productive time (NPT): hours lost to equipment failures, stuck pipe, waiting on weather or waiting on materials.
The daily drilling report, which records depth, operations, mud properties, costs and incidents every 24 hours, is the backbone of that analysis. Capturing it accurately at the rig site, rather than retyping it later, is exactly the kind of field data work SandApps focuses on.